Capacity Availability in Italy<>Greece interconnection

GR-IT HVDC cable

Due to a failure in the GRIT HVDC cable, it will be out of service approximately till middle of April 2025 and both TSOs (TERNA & IPTO) are making efforts to implement the yearly maintenance of the GR-IT HVDC cable during that aforementioned period instead of the initially scheduled period during 27/05/2025 – 23/06/2025.

Consequently, NTC IT<>GR  will be zero (0) MW  and the Long Term Transmission Rights that they have been already allocated for the aforementioned period will be curtailed in compliance with the HAR.