Capacity Availability in Greece-North Macedonia Interconnection

Increase NTC GR->NMK border direction

After performing security calculations at the SEE region, the NTC will be increased in GR->NMK border direction as below:

  • NTC = 250 MW  from 10/04/2022 till 15/04/2022

  • NTC = 350 MW  from 16/04/2022 till 30/04/2022

The extra capacity will be allocated on daily auctions in accordance  SEE CAO Auction Rules.