We inform you that you can find on our website, the new version of the Unit Maintenance Schedule for the Reliability Year 2017-2018.
In this version (version 4), the maintenance of the unit Amyndeo 2 will start after the maintenance of the units Megalopoli 3 and Megalopoli 4 and the maintenance of kardia 4 is transferred to 18/8/2018. The maintenance of the GT2 of Megalopoli 5 is postponed for the next Reliability Year.
Moreover, after the justified request of the Producer Protergia S.A., the maintenance of the unit Protergia is extended to 60 days and the maintenance of the unit Korinthos Power will start on 27/5/2018.