Service outage in the Greece Italy interconnection (upd)
Starting from 08:00 (CET) on 10.07.2013 the HVDC interconnection between Greece and Italy was set under repair due to fault on the underground cable.
Based on information from TERNA works should be completed in around 20 days.
For the timeperiod stated above the Physical Transmission Rights (PTRs) will be curtailed according to Auction Rules.