Change of unit maintenance schedule for thermal units
After the justified request of the producer PPC and in addition with the low forcasted load demand, the scheduled annual maintenace of the unit MELITI has been modified as follows:
- · The new maintenance period of the unit MELITI will be from 02 of August to 08 of September 2013 instead of the previous scheduled perion that was from 12 of October to 10 of November 2013.