Announcement for the Increase of NTC value the period 1 October - 8 October 2017 for the interconnection with FYROM

Announcement for the Increase of NTC value the period 1 October - 8 October 2017 for the interconnection with FYROM
In accordance to new calculations, the NTC between Greece and FYROM  is increased by 50MW  the period 1 October – 8 October 2017  for direction from FYROM to Greece i.e NTC=350MW. This quantity (50 MW) will be allocated by SEE CAO  on daily auctions in accordance with relevant Auction Rules.