We inform you that after the justified request of producer PPC S.A., an unplanned maintenance of the GT2 AHS Komotinis will be conducted from 28/04/2022 to 08/05/2022.

We inform you that after the justified request of producer MYTILINEOS S.A., the maintenance of the Steam Turbine (ST) of thermal unit Alouminio, scheduled to start on 13/01/2022, is postponed.

We inform you that the Annual Interconnections Maintenance Schedule for 2022 has been published here.

Please be informed that in the context of the 2 year Production Units Maintenance plan, in compliance with Article 3.11 of the System Operation Code, the Units Maintenance Schedules for the next two (2) Calendar Years have been published:

We inform you that according to the latest information from TERNA, the HVDC link outage is prolonged until 14/07/2021.

We inform you that after the justified request of producer PPC S.A., the maintenance of gas turbine No2 (GT2) of thermal unit Komotini, is prolonged until Friday 18/06/2021.