SECTION IV INTEGRATED SCHEDULING PROCESS
CHAPTER 9 HELLENIC ELECTRICITY TRANSMISSION SYSTEM OPERATOR OBLIGATIONS
Article 9.4 Determination of Zonal/Systemic Balancing Capacity Needs

The HETS Operator shall determine the zonal and systemic needs in Balancing Capacity for the (a) FCR, (b) aFRR and (c) mFRR, in order to ensure an adequate system response/regulation/reserve within the acceptable limits as established in the HETS Grid Code, taking into account the particular characteristics of the HETS, as defined in the ‘Methodology for Determination of Zonal/Systemic Balancing Capacity Needs’, which is approved by the RAEWW following a proposal by the HETS Operator in accordance with the provisions of paragraph 4 of Article 18 of Law 4425/2016.