We inform you that after the justified requests of the producers MYTILINEOS S.A. and PPC S.A., the Units Maintenance Schedule is updated. The updated (version 11) Units Maintenance Schedule is here.

We inform you that after the justified request of producer MYTILINEOS S.A., the maintenance of the ST of thermal unit Alouminio, is postponed.

We inform you that after the justified request of producer PPC S.A., the maintenance of gas turbine No2 (GT2) of thermal unit Komotini, is prolonged until Friday 18/06/2021.

We inform you that after the justified request of producer PPC S.A., the maintenance of gas turbine No2 (GT2) of thermal unit Komotini, is prolonged until Tuesday 15/06/2021.

We inform you that after the justified request of producer MYTILINEOS S.A., the maintenance of thermal unit Korinthos Power, is prolonged until Sunday 23/05/2021.

We inform you that after the justified request of producer ELPEDISON S.A., the maintenance of thermal unit Elpedison Thess, will take place on 08/04/2021 only. The unit will be available on 09/04/2021.