Consumers on the island of Folegandros are now supplied with electricity from the mainland system via Naxos and Santorini through a robust high-voltage network.
This development confirms the successful operation of the submarine cable system installed by IPTO as part of the southern Cyclades electrical interconnection, a project with a total budget of €385.7 million. Construction of the new interconnection, which includes the islands of Santorini, Folegandros, Milos and Serifos, was completed in June.
The Santorini-Folegandros section uses a 60 km, 150 kV high-voltage cable, with integrated optical fibres. It was laid at a maximum depth of 340 metres and buried along its entire submarine route for protection.
The high-voltage substation built by the Operator on Folegandros incorporates state-of-the-art gas-insulated switchgear (GIS), contributing to a minimal environmental and visual impact. Particular attention has also been paid to the architectural design of the building, which features stone cladding to ensure that it blends harmoniously with the local built and natural environment.
The electrical interconnection of the southern Cyclades brings their energy isolation to an end, substantially advancing their sustainable development and enhancing their tourism offering. At the same time, the retirement of the polluting oil-fired plants used for local electricity generation delivers significant environmental benefits for the Aegean ecosystem by reducing CO2 emissions.
The Minister of Environment and Energy, Mr. Stavros Papastavrou, stated: "Folegandros is leaving energy isolation behind and connecting to the mainland system. This is a significant step towards securing the island’s electricity supply, reducing electricity generation costs and protecting its unique natural environment. The interconnection of the southern Cyclades demonstrates how investment in energy infrastructure can improve people’s daily lives and support the development of our islands. For us, the energy transition delivers real value when its benefits reach every community and every citizen. I would like to thank IPTO, its employees and the local communities for their cooperation. We are moving forward with a clear plan for the interconnections across the Aegean, to strengthen the energy security of our islands and create better living conditions for their residents".
IPTO Chairman and Chief Executive Officer, Mr. Manos Manousakis, stated: "Folegandros is now part of the interconnected electricity system. Thanks to the modern infrastructure developed by the Operator in the Cyclades in recent years, islands that make a significant contribution to the country’s tourism industry enjoy a high level of energy security, even during periods of peak demand. The interconnection of the southern Cyclades, which completes the integration of this island group into the high-voltage grid, was a technically complex project that contributed even further to IPTO’s expertise. With the forthcoming energisation of the Santorini, Milos and Serifos interconnections, yet another major chapter for energy projects across the Aegean is coming to a close".
The project received €164.5 million in EU funding through the Greece 2.0 – Recovery and Resilience Facility. The European Investment Bank also contributed to the financing through a €157 million direct loan agreement signed by IPTO and a second loan agreement of €108.4 million, supported by funds from the Greece 2.0 – Recovery and Resilience Facility.