We inform you that after the justified request of producer HERON S.A., the scheduled annual maintenance of thermal unit HERON S.A. for the period 13/10/2023 to 19/10/2023, is cancelled.
We inform you that after the justified requests of the producers PPC S.A. and HERON S.A., the Units Maintenance Schedule 2023 is updated. The updated (version 6) Units Maintenance Schedule is here.
We inform you that after the justified request of producer PPC S.A., the annual maintenance of Gas Turbine 2 of thermal unit Lavrio 4, is extended till 04/06/2023.
We inform you that after the justified request of producer PPC S.A., maintenance works will be conducted in thermal unit Aliveri 5, from 03/06/2023 to 08/06/2023.
We inform you that after the justified request of producer HERON S.A. the Heron 1, Heron 2 and Heron 3 thermal units annual maintenance schedule is modified as follows:
Dyrrachiou 89 & Kifissou, 104 43 Athina
+30-210-5192101
GEMI No: 004001001000