ISP

Integrated Scheduling Process

Due to works on the 150kV Transmission Line S/S KORINTHOS – S/S ARGOS ΙI, on 24-11-2021, 09:00 – 13:00, restrictions may be imposed which could affect the production of Units in the area.

We inform you that according to the latest information from TERNA, the HVDC link outage is prolonged until 14/07/2021.

On Tuesday, May 18, 2021, a fault was found in the HVDC link between Greece and Italy. The HVDC link will be out of operation until the fault is restored.

We inform you that today Wednesday 14/10/2020 there will be a temporary shutdown of the Market Management System (MMS) & Authentication System from 15:00 to 18:00 due to necessary maintenance and upgrade works. The Balancing Market Management System (BMMS) will also be affected from the aforementioned maintenance works and will be unavailable at the same period of time.