We inform you that after the justified request of producer MYTILINEOS S.A., the annual maintenance of thermal unit Korinthos Power, is extended till 20/04/2022.

We inform you that after the justified request of producer PPC S.A., an unplanned maintenance of the GT2 AHS Komotinis will be conducted from 28/04/2022 to 08/05/2022.

Due to necessary maintenance works in the Transmission System and specifically on the Transmission Line 150kV S/S KORINTHOS - AIS MEGALOPOLIS A, from Friday 18/2/2022 to Tuesday 22/2/2022, constraints may be imposed that could affect the unit production in the area.

We inform you that after the justified request of producer MYTILINEOS S.A., the maintenance of the Steam Turbine (ST) of thermal unit Alouminio, scheduled to start on 13/01/2022, is postponed.

We inform you that the Annual Interconnections Maintenance Schedule for 2022 has been published here.

Please be informed that in the context of the 2 year Production Units Maintenance plan, in compliance with Article 3.11 of the System Operation Code, the Units Maintenance Schedules for the next two (2) Calendar Years have been published: