Balancing Market

Day Ahead Market

We inform you that after the justified request of producer PPC S.A., the annual maintenance of thermal unit Lavrio 5, is shifted by one day and will be conducted from 11/9 to 16/9.

We inform you that based on the Transmission System's current conditions, IPTO deems it necessary to temporarily postpone the initiation of the annual maintenance of thermal unit Protergia CC. New maintenance period from 12/09/2022 to 08/12/2022.

Following information from the Italian TSO (TERNA), we inform you that the outage of the Greece-Italy DC-link, which occurred on Friday 12/08, at 14:51, due to a fault on TERNA’s side, is expected to last until Friday August 19, 2022 according to TERNA’s estimates. Therefore, until the restoration of the DC-link, the NTC of the Greece-Italy interconnection is set to zero in both directions.

Due to necessary maintenance works in the Transmission System and specifically in Circuit 400kV HVSS AG. STEFANOS (853,873) - HVSS PALLINIS (853,873), until Tuesday 24/2/2022, 14:00, constraints may be imposed that could affect the unit production in the area.

Due to necessary maintenance works in the Transmission System and specifically on the Transmission Line 150kV S/S KORINTHOS - AIS MEGALOPOLIS A, from Friday 18/2/2022 to Tuesday 22/2/2022, constraints may be imposed that could affect the unit production in the area.

We inform you that following the justified request of producer ELPEDISON S.A., the start of the annual maintenance of ELPEDISON THISVI is deferred from 5/4/2025 to 6/4/2025.