The HETS Operator shall keep a Dispatchable Load Portfolio Registry for the registration of the Dispatchable Load Portfolios that have successfully completed the relevant pre-qualification tests described in the Technical Decision “Process and Prequalification Tests for BSPs”.
The information included in the Dispatchable Load Portfolios Registry and any supporting documents required for registration therewith are described in detail in the Technical Decision “Procedures of Registration with the HETS Operator Registry”. The Aggregator of Dispatchable Load Portfolios submits, together with the registration documents, a technical report stating, under the responsibility of the Aggregator, the technical readiness for the provision of Balancing Services.
Each Response Demand Aggregator and each Consumer participating in the Balancing Market as Balancing Service Provider is obliged to immediately notify the HETS Operator of any changes in the data held in the Dispatchable Load Portfolios Registry. The HETS Operator determines whether any upcoming change in the technical characteristics of the Portfolio requires the re-performance of prequalification tests for the Portfolio, either in whole or in part, as defined in the Technical Decision “Process and Prequalification Tests for BSPs”. To conduct the new prequalification tests, the Demand Response Aggregator or the Consumer pays again 50% of the registration fee as applicable for Balancing Service Entities.
Each Dispatchable Pumped-Storage hydro Generating Unit shall be a distinct Dispatchable Load Portfolio. The Producers representing the above Units are obliged to immediately notify the HETS Operator of any changes in the data held in the Dispatchable Load Portfolios Registry.
Placement of a Load Portfolio with Demand Response capability under commissioning operation or under execution of prequalification tests requires prior registration in the Dispatchable Load Portfolio Registry.
The HETS Operator maintains a Table of Meters for the Dispatchable Load Portfolios, which clearly indicates the meters of the loads included in each Portfolio of the Demand Response Aggregator, as described in the Technical Decision “Procedures of Registration with the HETS Operator Registry”. The HETS Operator sends the above table to HEDNO for the purposes of the settlement procedure.
SECTION II REGISTRATION OF PARTICIPANTS
CHAPTER 5 REGISTRIES OF ENTITIES
Article 5.4 Dispatchable Load Portfolio Registry