Αφιέρωμα       Feature




                                                                                     Project's Progress


                                                The Crete-Attica electricity interconnection was completed in December 2024,
                Η πόντιση και προστασία          in a record time of just four and a half years from contract signing (June 2020),
            των 2 καλωδίων συνεχούς ρεύματος                                  and entered into operation in May 2025.
            υψηλής τάσης (HVDC), μήκους 336
            χλμ. το καθένα, ολοκληρώθηκε τον   Ολοκληρώθηκε η κατασκευαστική      Τον Ιανουάριο, ολοκληρώθηκε
           Μάρτιο και τον Μάιο για τον ανατολικό   φάση της διασύνδεσης με την        επιτυχώς η δοκιμή
            και δυτικό πόλο αντίστοιχα, ενώ οι   εγκατάσταση του συνόλου του         μετά την εγκατάσταση
            δοκιμές μετά την εγκατάσταση του   εξοπλισμού των Σταθμών Μετατροπής   για το σύνολο του καλωδιακού
           υποβρύχιου καλωδιακού συστήματος   και του Υποσταθμού GIS, ενώ παράλληλα   συστήματος, ενώ τον Μάιο
           ολοκληρώθηκαν τον Δεκέμβριο. Το ίδιο   εκκίνησε και η διαδικασία των     και μετά την ολοκλήρωση
          έτος πραγματοποιήθηκε η ολοκλήρωση   προκαταρκτικών δοκιμών. Επίσης, εντός   των προκαταρκτικών δοκιμών
          της κατασκευής των βασικών κτηρίων και   του ίδιου έτους ολοκληρώθηκε και   ξεκίνησε η μεταφορά των πρώτων
           η ανέγερση των Μετασχηματιστών του   η εγκατάσταση των HVDC καλωδίων      ηλεκτρικών φορτίων
            Σταθμού Μετατροπής στην Αττική.    στο χερσαίο τμήμα της όδευσης.    από την Αττική προς την Κρήτη.

                    2023                              2024                              2025


             The laying and protection of the   The construction phase of the      In January, post-installation
              2 high voltage direct current   interconnection was concluded with      testing of the entire
            (HVDC) cables, each 336 km long,   the installation of all equipment   cable system was successfully
                was completed in March       at the Converter Stations and the GIS   completed, and in May,
            and May for the east and west poles   Substation, while the preliminary testing   following the completion
            respectively, while post-installation   process was launched in parallel.   of preliminary tests,
                testing of the submarine           During the same year,           the transmission of the first
              cable system was completed      the installation of the HVDC cables      electrical loads
            in December. That same year, the   along the land section of the route    from Attica to Crete
           construction of the main buildings and   was also completed.                 commenced.
             the erection of the Transformers
             at the Attica Converter Station
                 were also completed.















                                                                     A cutting-edge infrastructure
                                                                     that links Crete with the

                                                                     national power grid,
                                                                     reshaping the country’s
                                                                     energy landscape.