We inform you that following the justified request of the producer PPC S.A., the annual maintenance of unit Lavrio 4, will be conducted as follows:

  • 12/9-28/9 Steam Turbine (ST)
  • 12/9-18/9 Gas Turbine Νο1 (GT1)
  • 19/9-23/9 Gas Turbine Νο2 (GT2)
  • 24/9-28/9 Gas Turbine Νο3 (GT3)