17.03.2023

HERON 1, 2, 3 annual maintenance update

HERON 1, 2, 3 annual maintenance update

We inform you that after the justified request of producer HERON S.A. the Heron 1, Heron 2 and Heron 3 thermal units annual maintenance schedule is modified as follows:

  • Heron 1: 23/09/2023 to 07/10/2023
  • Heron 2: 20/03/2023 to 22/03/2023
  • Heron 3: 23/03/2023 to 25/03/2023