CAPACITY AVAILABILITY AT GREECE-ITALY INTERCONNECTION (Updated) 30.11.2018

30.11.2018

With reference to the notice published on November 13th 2018 on this website about the unavailability of the link between Italy and Greece, TERNA and ADMIE inform market participants that the cable will be back in operation on Saturday 1st of December and the NTC will be restored at 500 MW (starting from 0:00 CET) on both directions.

Consequently on the 30th November will be held the daily auction for the 1st December.