Unit Maintenance Schedule amendment

15.10.2018

After the justified request of the Producer PPC S.A., we inform you that the maintenance of the unit No3 will finish on 22 of November 2018. Due to the above prolongation, the 35-days scheduled maintenance of the unit No5 is cancelled, and instead of this the unit will be held from 16 to 22 of October 2018.